Ratios & Percentageshard
0:00.0

A project is divided into three stages: Planning, Execution, and Review, with work times in ratio 1:3:21:3:2. If the Planning phase starts on Day 1 and each phase must be completed before the next begins, and the company decides to increase the Execution phase time by 50%50\% while decreasing the Review phase time by 25%25\%, what is the percentage change in the total time required for the project?